Lake and Lathrop lops off one floor, submits building permits

Developer sends necessary soil remediation docs to EPA

Share on Facebook
Share on Twitter
Print

By Maria Maxham

Staff Reporter

The mixed-use development project at Lake and Lathrop in River Forest may finally take off, as the developer submitted new project plans on Dec. 16. These plans call for eliminating one floor from the original five-story plan, with 22 condominiums rather than 33 units. The building is still mixed use, with commercial on the ground level and residential above that.

The developer, Lake and Lathrop LLC, which is comprised of Sedgwick Development and Keystone Ventures, has been granted extensions in the past, most recently receiving permission from the village board to extend the permit application deadline from June 17, 2019 to Dec. 15, 2019, which pushed out dates for breaking ground and project completion.

These was some frustration from village trustees during this process, and Trustee Patty Henek voted against the extension. Trustee Tom Cargie voted for the extension but said he would not do so again.

"This is the last extension I will vote for," said Cargie. "It seems like a continuous process of delays. There will be no more excuses moving forward."

Although the original plan was for a five-story building, Village President Cathy Adduci said that since the development review board initially approved the 5-story development, the developer can build less; developers can go below but not above the original approved scope. These new plans, for a 4-story building, fall under the original approval since they are less than the approved structure.

In an email, Village Administrator Eric Palm said that Lake and Lathrop LLC has also sent the necessary reports and documents to the Illinois Environmental Protection Agency (IEPA) to ensure that soil remediation has been completed.

It will be about two to three months before the plans are fully reviewed by an architectural engineering firm outsourced by the village. If everything meets village approval, the permit will be given to Lake and Lathrop LLC sometime around May, at which time, per zoning code, the developer has 15 months to complete the project.

Love the Journal?

Become our partner in independent community journalism

Thanks for turning to Wednesday Journal and OakPark.com. We love our thousands of digital-only readers. Now though we're asking you to partner up in paying for our reporters and photographers who report this news. It had to happen, right?

On the plus side, we're giving you a simple way, and a better reason, to join in. We're now a non-profit -- Growing Community Media -- so your donation is tax deductible. And signing up for a monthly donation, or making a one-time donation, is fast and easy.

No threats from us. The news will be here. No paywalls or article countdowns. We're counting on an exquisite mix of civic enlightenment and mild shaming. Sort of like public radio.

Claim your bragging rights. Become a digital member.

Donate Now

Reader Comments

No Comments - Add Your Comment

Note: This page requires you to login with Facebook to comment.

Comment Policy

Facebook Connect

Answer Book 2019

To view the full print edition of the Wednesday Journal 2019 Answer Book, please click here.

Quick Links

Sign-up to get the latest news updates for Oak Park and River Forest.


            
SubscribeClassified
MultimediaContact us
Submit Letter To The Editor
Place a Classified Ad